Updated 7 days ago58 ft of conduit installation
One new manhole west of Harle Court
Continued to October 20th meeting
On October 6, 2026, NSAR electric company, represented by Amy Mcweeny on behalf of Eversource Energy, petitioned the Woburn City Council for a grant of location to install approximately 58 ft of conduit and one manhole west of Harle Court in Main Street to improve support and capacity in the area. The council voted to continue the matter until their regular meeting on October 20th, pending a memo from the DPW or city engineer. The public hearing was opened and closed with no audience comments.
Read more at the source Woburn Public Media Center